GASCO awards EPC contract for Asab Gas Development Project
A statement issued by GASCO and received by the Emirates News Agency, WAM, said that the Letter of Award was issued in Abu Dhabi on 12th July 2005. The project will be managed from Bechtel's office in Huston, Texas, USA, and is scheduled for completion within thirty eight (38) months including successful test runs.
GASCO underlined that the AGD-II project is a mega project and is one of the largest and the last of the five EPC Packages within the overall scheme of onshore gas developments launched by ADNOC.
The project is designed to treat 800 Million Standard Cubic Feet per Day MMSCFD to recover 6400 (Six Thousand Four Hundred) Tons Per Day of Natural Gas Liquids(NGL) from the existing Asab Gas Plant(AGP).
GASCO stated that it implements this project on behalf of ADNOC, Abu Dhabi National Oil Company, with support of M/s VECO, Canada, as the project Management Consultant.